gc-improv merge plan (will need trunk freeze)
Laurynas Biveinis
laurynas.biveinis@gmail.com
Thu Jun 3 06:44:00 GMT 2010
2010/6/2 Richard Guenther <richard.guenther@gmail.com>:
> On Wed, Jun 2, 2010 at 1:51 PM, David Edelsohn <dje.gcc@gmail.com> wrote:
>> On Wed, Jun 2, 2010 at 2:07 AM, Laurynas Biveinis
>>> All the patches from gc-improv merge have been approved. Due to the
>>> scope of the changes, the merge will need trunk freeze. Thus I am
>>> planning to do it next Tuesday, at 7am CEST. The freeze should last
>>> about 2-3 hours.
>>
>> Major merges should not freeze the trunk for hours but for a day. We
>> should ensure that the trunk is quiescent before the merge and allow
>> other developers to update and test before intermixing other patches.
>
> Yes, I'd say we freeze late on Monday and unfreeze on Wednesday.
OK, late Monday to Wednesday it is then. Thanks for advice.
--
Laurynas